What we residents know about this project is in the 5/13/25 board meeting packet on pages 103-107
Key Points in Packet Information
Cost to Township $1,200,000 – $1,400,000 plus property acquisition costs.
Total cost $12,000,000 – $14,000,000
Large Federal grant to RCOC.
“Hundreds of trees to be removed”.
“Property acquisition” (For what? Traffic Circle??)
Manager Joe Merucci said that RCOC wants approval by May.
We paid $48,000 for the study so far.